Hollomon_parameter

TT INTEGRITY ENGINEERING TOOL

Cumulative Hollomon–Jaffe Heat-Treatment Assessment

Calculate cumulative Hp exposure from consecutive tempering, PWHT and stress-relieving cycles.

v1.2
01

Consecutive heat-treatment cycles

How ramp data is used

Heating/cooling rate determines the real ramp duration and the slope of the time–temperature diagram.

Ramp contribution to Hp is a separate, optional equivalent-time correction. The published implementation used here is limited to the C = 20 form.

Still-air release below the controlled-cooling transition is identified, but no fictitious cooling time is added without measured thermal data.

Report information entered once and reused throughout the calculation and engineering report
Material / material family Select an EN, EN 10213 or ASME/ASTM material. The catalogue Pcrit is shown after selection.
Governing wall thickness
Used for tempering records and automatic heating/cooling-rate rules.
Cumulative-cycle method Each entered cycle is converted to an equivalent time at the highest cycle temperature. Equivalent times—not individual Hp values—are summed to obtain the cumulative Hp exposure. Governing thickness is mandatory for tempering records and automatic heating/cooling-rate rules.

Automatic presets calculate maximum controlled rates from governing thickness. The controlled profile is time-proportional; any release to still air below the preset transition temperature is identified separately and its duration is not invented.

02

Cumulative Hp result

Total Hp parameter

18.132 dimensionless
Enter one or more heat-treatment cycles to calculate the cumulative Hp exposure.
03

Equivalent holding conditions

Orientation at the calculated Hp and, when available, at the selected material Hp_max / Pcrit. Ramp contributions are not applied a second time.

Calculated condition

Current Hp

Hp = 18.132
Temperature Equivalent time, min Time in hours

Engineering calculation aid only. This output is not an approved heat-treatment procedure, material qualification, code-compliance certificate or instruction to perform heat treatment. Verify all inputs, the selected H–J constant, governing thickness, empirical rate rule, holding requirements, material limits, applicable standard and approved procedure. Controlled cooling is plotted using the applied calculated rate; still-air cooling below a release temperature is identified but its unknown duration is excluded unless supported by measured thermal data. Final engineering approval remains with the responsible engineer and organisation.